One of the most frequent questions we hear at Varilko Remodeling is: How long does a bathroom remodel take Atlanta contractors to complete?

The short answer is: it varies based on scope, but a realistic, high-quality renovation should not be rushed. While a quick facelift might take a week or two, a full, professional renovation—the kind that adds lasting value—requires careful sequencing and skilled labor.

Understanding the typical bathroom renovation timeline Atlanta homeowners should expect helps you manage expectations and plan for the temporary disruption. Here is a breakdown of the phases and typical duration for a complete remodel.

1. Timeline Estimates by Scope (Active Construction)

The size and complexity of the bathroom dictate the construction time. Note that these estimates reflect the active construction phase only (after planning and materials are secured).

  • Powder Room/Half Bath: Typically takes 1 to 2 Weeks. This involves simple fixture swaps, basic tile work, and painting.
  • Standard Full Bath: Typically takes 3 to 4 Weeks. This includes a full gut, new plumbing/electrical rough-in, tub/shower conversion, and new tile installation.
  • Master Bath Remodel: Typically takes 5 to 7 Weeks. This often involves a full gut, complex tile work (like a wet room), custom vanity installation, and potential layout changes (plumbing relocation).

2. The Complete Bathroom Renovation Timeline (Phases)

A successful remodel is separated into three critical phases, each with its own duration.

Phase A: Planning and Design (4–8 Weeks)

This phase happens entirely before we swing a hammer, and it is the most critical for avoiding delays later.

  • Consultation & Quote: (1 Week) Initial meeting, site assessment, and detailed estimate.
  • Material Selection: (1–3 Weeks) Finalizing every fixture, tile, vanity, and hardware piece. Delays here cause cascading delays later.
  • Permitting: (2–4 Weeks) Submitting plans to the local Atlanta jurisdiction and awaiting approval. (See our guide on permits).

Phase B: Rough-In and Construction (4–7 Weeks)

This is the active, noisy phase of the job. It requires precision and proper drying time.

  • Demolition: (1–2 Days) Tearing out old fixtures, tile, and walls down to the studs.
  • Rough-In Trades: (1 Week) New framing, electrical wiring, and plumbing pipes/drains are installed and inspected.
  • Waterproofing & Prep: (3–5 Days) Installing cement board, applying waterproofing membranes (crucial drying time), and ensuring the subfloor is ready for tile.
  • Tiling: (1–2 Weeks) Laying floor tile, shower tile, and niche tile. This includes cutting, setting, and grout curing time.
  • Inspections: (1–2 Days Intermittent) Required city inspections of rough-in and waterproofing.

Phase C: Finish and Finalization (1–2 Weeks)

This is where the room becomes functional and beautiful again.

  • Installations: (3–5 Days) Setting the vanity, toilet, faucets, final electrical trims (lights, outlets), and painting.
  • Glass/Custom Work: (1–2 Days) Installing the frameless glass shower door/enclosure (typically measured after tile is complete).
  • Final Touches: (1–2 Days) Deep cleaning, hardware installation, and final touch-ups.

3. Factors Affecting Your Remodel Schedule

While we strive to adhere to the initial Varilko construction timeline, several factors commonly affect the duration of Atlanta remodels:

  • Scope Creep: Changing your mind on materials or adding features (like heated floors) mid-project will always add time and cost.
  • Material Availability: Custom cabinets, specific high-end tile from overseas, or specialty fixtures often have lead times of 6–12 weeks. Securing all materials before demolition begins is the key to staying on schedule.
  • Unforeseen Issues: This is common in older Atlanta homes. Rotten subfloors, unexpected plumbing lines behind walls, or mold discovery require remediation and subsequent inspections, adding days to the timeline.

A transparent and realistic timeline is the foundation of a successful renovation. When you partner with Varilko Remodeling, we manage the schedule meticulously, coordinating trades and materials to deliver your new bathroom efficiently and to the highest standard.

Ready to Start Planning Your Bathroom Transformation?

Don’t guess at your project’s duration. Contact us for a detailed, phase-by-phase master bath remodel duration estimate based on your specific Atlanta home.